Calculate my Bill

The System calculation of Bills is solely dependent on volume consumed at each band.                                                                

There are two Volume categories: Band-1 and Band-2.                                                              

The Bill is calculated progressively at the Band in which the Volume consumed falls in.  

 Volume Category

Water

 Sewer

From

To

Rate per kL

From

To

Rate per kL

Band-1

1 kL

15 kL

1.5

1 kL

15 kL

0.50

Band-2

>15 kL

 

7.50

>15 kL

 

2.50

 

For example: Customer consumes 75kL within a month                                                                                                             

The first 15kL @ Band-1 (15x1.50 = K22.50), the next 60kL @ Band - 2 (60x7.50 = K450.00)                                                                        

Thus the charge would be:       K22.50+K450.00 = K472.50 (Add 10% GST = K519.75)                               

                                                                                

If the customer is connected to the Sewer, the same principle applies:    

The first 15kL @ Band-1 (15x0.50=K7.50), the next 60kL @ Band-2 (60x2.50 = K150.00)

Thus the charge would be:       K7.50+K150.00 = K157.50 (Add 10% GST = K173.25)                               

  

The total invoice charge now would be:   

                                                      Water charge + Sewer Charge                          

                                                           K519.75   +   K173.25                

                                                          = K693.00 Total Payable